September 2025
Package 1 - Raichur - Gadwal

Progress Status September’25

Ch:211+440 to 211+550 BHS GSB top sectioning work in progress
Ch:211+440 to 211+550 BHS GSB top sectioning work in progress
DBM 1st laying Ch 211+400 to 211+560KM BHS
DBM 1st laying Ch 211+400 to 211+560KM BHS
225+794 mnb A1 Dirt wall with bracket RHS concrete work in progress
225+794 mnb A1 Dirt wall with bracket RHS concrete work in progress

 

GSB-top-watering-work-in-progress-from-ch-226450-to-226775-LHS
GSB-top-watering-work-in-progress-from-ch-226+450-to-226+775-LHS

 

CH-237140-LHS-EMBANKMENT-LAYER-GREADING-AND-ROLLING-WORK-IN-PROGRES
CH-237+140-LHS-EMBANKMENT-LAYER-GREADING-AND-ROLLING-WORK-IN-PROGRES

 

DBM Core Cutting conducted in the presence of IE Team at-220+150-RHS
DBM Core Cutting conducted in the presence of IE Team at – 220+150-RHS

 

FDD-test-conducting-at-km.-211540-to-211+700-RHS-at-WMM-level
FDD-test-conducting-at-km.-211540-to-211+700- RHS-at-WMM-level
SG top work in progress from ch-225+953 to 226+020 BHS
SG top work in progress from ch-225+953 to 226+020 BHS
DBM 1st laying Ch 211+400 to 211+560KM BHS IE & concessioner site visit
DBM 1st laying Ch 211+400 to 211+560KM BHS IE & concessioner site visit