Ch:211+440 to 211+550 BHS GSB top sectioning work in progressDBM 1st laying Ch 211+400 to 211+560KM BHS225+794 mnb A1 Dirt wall with bracket RHS concrete work in progress
DBM Core Cutting conducted in the presence of IE Team at – 220+150-RHS
FDD-test-conducting-at-km.-211540-to-211+700- RHS-at-WMM-levelSG top work in progress from ch-225+953 to 226+020 BHSDBM 1st laying Ch 211+400 to 211+560KM BHS IE & concessioner site visit