Package 1 - Raichur - Gadwal

Progress Status October’25

211+100 to 211+300 RHS median edge w-beam erection in progress
211+100 to 211+300 RHS median edge w-beam erection in progress
Ch 205+650 RHS Bus shelter post installation
Ch 205+650 RHS Bus shelter post installation
DLC laying work in progress from ch-228+450 to 228+580 RHS SR for toll booth
DLC laying work in progress from ch-228+450 to 228+580 RHS SR for toll booth
Stone pitching 203+150 to 203+250Km
Stone pitching 203+150 to 203+250Km
A1-P1 Deck slab concrete started at ch- 241+775(vup)
A1-P1 Deck slab concrete started at ch- 241+775(vup)
BC Laying
BC Laying 
215+610 To 215+660 Geostrap Laying
215+610 To 215+660 Geostrap Laying
Surface regulatory test conducted in presence of IE Representatives on BC top layer, location 235+600 to 236+500 LHS
Surface regulatory test conducted in presence of IE Representatives on BC top layer, location 235+600 to 236+500 LHS
FDD testing @ 236+580 to 236+820 BHS
FDD testing @ 236+580 to 236+820 BHS
214+200 LHS friction slab erection in progress
214+200 LHS friction slab erection in progress